What has changed?

In July 2026, the Planning Act changed, impacting how local councils approach and engage with the early stages of a Development Consent Order (DCO) process for Nationally Significant Infrastructure Projects (NSIPs).
 
The changes to the Planning Act are intended to accelerate the NSIP process. It was envisaged, with the former model, the DCO process would take two years from pre-application consultation to securing consent from the Government, which in practice has varied. The revised process is expected to reduce the process to around 12 months in some cases.

This article explains how these changes affect parish and town councils and will impact how you need to approach your work.
Under the new protocol, being proactive, doing preparation and being prepared to get involved early has never been so important.
Below, are stages of the process that have changed, and what it means to parish and town councils.
 
1. Removal of Statutory Consultation (pre-application stage)

Before

Applicants were legally bound to engage the public and stakeholders in statutory consultation through the production of a Preliminary Environmental Information Report (“PEIR”) and demonstrate compliance as part of the process.

Now

The statutory consultation requirement has been removed. Developers are still strongly encouraged to engage with communities and councils, but the extent and quality of engagement is largely their decision. It may not be as thorough. Also, the level of pre-application engagement is now not a determining factor in whether an application is accepted and consented.
However, Government emphasises that consultation remains a mechanism for identifying and resolving issues with projects, which is in a developer’s best interest. There may be a large degree of variation between developers in terms of how engagement is carried out.

What this means for you
- Pre-application stage engagement is still the best time to get involved because you will have more influence over the project plans.
- Do not assume you will receive plenty of advance notice of a project. If an NSIP consultation takes place, it can happen at very short notice – taking everyone by surprise and possibly leaving you without an opportunity to influence a project.
- Any council in Suffolk could be involved in an NSIP, so you need to be ready to act.
- Being prepared has never been so important. Without the statutory requirement to consult with local people, you need to be very pro-active to engage with communities and other stakeholders to gather concerns, support or ideas, and submit to the developer.
- The principles of effective responses to consultation have not changed, and it is still important to follow the mitigation hierarchy and engage with the project, even if the local council is opposed to the scheme.
 
What you need to do
- Familiarise yourself with the resources on the SALC website, which offer guidance across the entire NSIP planning process. 
Prepare for an NSIP arriving by agreeing procedures to organise additional meetings if necessary, to ensure consultation responses can be prepared and submitted.
- If multiple rounds of consultation are held (which is particularly applicable for the larger schemes) you can provide constructive feedback to the developer about their engagement, and facilitate improved engagement in the future. Monitor emerging infrastructure proposals on the Planning Inspectorate website and sign up for email updates for the project page on the Planning Inspectorate’s website, and on the developer’s website, once available. Track social media, the news and stay in touch with SALC, and county and district councils. Google alerts and free AI platforms are also helpful for tracking news. Build relationships with neighbouring councils, so you can pool the skills required to cope with the increased workload and specialist areas such as ecology. If the developer runs pre-application engagement opportunities, such as online and in-person events, make the most of them. Start year-round community engagement, so you have relationships in place before an NSIP arrives. A community is more likely to be involved if they already have a connection with you – this is especially important for reaching marginalised communities. - Contact other councils that have already gone through the NSIP process – ask for their advice and compare their unique NSIP project circumstances to your own. 
- Have ideas up your sleeve to raise money to fund the inevitable increased workload or additional resource, e.g. consider raising the precept or using reserves.
- Create a list of improvements in your community that you think the NSIP developer should pay for either as part of a project’s construction, or through the community funding they may provide once consent is given.
- Look through existing data from your previous community engagement – you potentially have ready-to-use evidence to weave into your feedback to the developer.
- Think about how you can support yourself and colleagues through the process as it can be very challenging, with the potential to health and wellbeing. Read this article for more information.
 
Source: www.gov.uk/guidance/planning-act-2008-guidance-on-preparing-an-application-part-1-pre-application-steps (Sections 3, 4 and 6)


2. Less environmental information may be available to you (pre-application stage)

Before
Developers used to publish a Preliminary Environmental Information (PEI) often in the form of a Preliminary Environmental Information Report (PEIR) during Statutory Consultation.
 
The PEI included key information such as the proposed scheme and site layout; preliminary findings of environmental surveys; initial assessments of traffic, noise, landscape, ecology, flooding, air quality and heritage; potential cumulative effects with other developments; proposed mitigation measures; and where assessments are ongoing.

Now
There is no longer a requirement for developers to publish PEI before finalising the Environmental Statement for the application to the Government. Developers may voluntarily publish environmental information before submitting their application (if they consider it appropriate). It is likely environmental information will be more targeted for particular areas of impact.
 
What this means for you 
 You may not see detailed environmental information and impacts until the application is submitted to government. Without PEI, there will be less time to identify issues and produce a response, e.g. expressing concerns about the developer’s work, sourcing help from a specialist advisor, influencing the developer's assessments.
 
What you need to do
- Be proactive: identify specialists in your area now for the areas covered by the PEI, e.g. traffic, flooding, landscape, heritage and ecology.
- It is still important to flag your environmental impacts of concern during the pre-application phase so your concerns can be considered by the developer when carrying out those assessments.
- Contact other local councils to invite them to collaborate. Time and resources for local councils are limited and there can be benefits in working together to exchange views, share knowledge and, where required, to share the cost of expert advice. Examining authorities will appreciate a clear, co-ordinated response from the local community in which issues are raised collectively.

Source: www.gov.uk/guidance/planning-act-2008-guidance-on-preparing-an-application-part-1-pre-application-steps (Section 5.7)

3. Relevant Representation and Written Representation has become more important (pre-examination stage)

Before
During Examination, the application is scrutinised and any outstanding issues, concerns and differing views are examined before a decision is made by the government. Historically, councils could treat a Relevant Representation (RR) and Written Representation (WR) largely as a notice of issues, and as a way of securing Interested Party status at pre-examination stage, enabling them to have a say on specific matters at hearings and through other channels.

This was helpful if you wanted to try to influence a specific issue when the government is examining outstanding issues in the application.

Now
Following the removal of pre-application statutory consultation, councils should now treat the RR as a statement/summary of their case, whilst recognising that the detailed evidence and analysis will still be provided through Written Representation (WR) and other examination documents during the examination. In terms of influencing the development, there is now more emphasis on this part of the process. Especially if the developer decided to do a limited public consultation voluntarily.
 
Further information on RRs – including the updated Government guidance on the role of these documents – is here: Nationally Significant Infrastructure Projects: How to register to have your say and make a relevant representation - GOV.UK

What this means for you 
 Your RR and WR may be the most important documents you submit – depending on whether the developer runs a pre-application consultation.
 
What you need to do 
- Have draft RR and WR templates ready in case an NSIP arrives – we suggest looking at the NSIPs section on the SALC website or contacting a council that has already gone through the process. If the latter, do not simply copy and paste their wording – include your specific information if you want to influence the outcome. You should have access to the full application documents during the period for submitting your RR and WR. If you have already submitted previous consultation responses, it is recommended you provide your views on where previous concerns have not been adequately addressed and why. Avoid vague statements such as "the project will be harmful" – be as specific as possible, specifying what changes the developer should make to address your concerns if possible. Clearly explain local impacts and provide evidence where possible. You may already have data that you can draw on, so have a good look through your folders and emails. 

Source: https://www.gov.uk/guidance/planning-act-2008-guidance-on-the-pre-examination-stage-of-an-application (Sections 2.5-2.15)
 

For more advice and support around NSIP community engagement, raise an issue via our Members Portal or email engagement@suffolk-alc.gov.uk.

 

For more ideas, get in touch with the team at SALC, or you can check out some more creative ideas in the GOV.UK 'Digital Community Engagement Toolkit'

Source: www.gov.uk/guidance/planning-act-2008-guidance-on-preparing-an-application-part-1-pre-application-steps (Sections 3, 4 and 6)